Navy Base Intermodal Facility Construction Update – Week of May June 2, 2025

  1. Construction will continue on Cosgrove Ave. between Noisette and N. Hobson. Pedestrians will be rerouted to use the sidewalk on the DHEC building side.
  2. Driveways on N. Hobson, north of McMillan, with the red squares will be closed off; those with green squares will be open.  (Page 4)
  3. Remaining project duration: The northbound and southbound Bainbridge Connector outside lanes will be closed for construction operations. Traffic will be shifted to the inside lanes. (Page 2)
  4. Paving at the intersection of Cosgrove and Spruill is complete. Access to the Cosgrove Bridge is still closed off.
  5. Traffic is now shifted onto the new alignment on N. Hobson.
  6. The entrance to Kilo Street will be closed off—traffic to be detoured down Supply Street.

Additional information concerning the NBIF project can be found here.